Every preventive maintenance schedule needs a rule for when it comes due. A calendar PM comes due on a date, whether or not the machine ran. A meter-based PM comes due when the hour meter reaches an interval, which suits equipment that runs a different number of hours each week. Oxmaint can set a schedule on either rule, or on both, due on whichever is reached first. Sign up to compare the rules on a sample PM register with 55 schedules.

Comparison · Calendar PM · Meter-Based PM · Run Hours

Calendar vs Meter-Based Preventive Maintenance

Dates, hours or both, and how to choose per machine rather than for the whole plant. Sign up and see each rule at work.

The Two Rules Side by Side

Calendar-basedMeter-based
Comes dueOn a date: every week, month or yearAt an hour-meter reading: every so many run hours
FollowsTime passing, whether the machine ran or notHow much the machine actually ran
SuitsInspections set by date, ageing parts, statutory checksWear that follows use: compressors, spindles, forklifts
NeedsNothing beyond the dateHour readings logged on the asset
Risk if used aloneWork done too early on a quiet machine, or too late on a busy oneA machine that barely runs is not looked at for a long time

Whichever Comes First

A schedule on both rules is due on the hours or the date, whichever is reached first. When the job is raised, the date and the hours both roll on, so the schedule is not instantly due again on the side that was not reached. Sign up to open one.

Sample schedule · CNC way lube, spindle and coolant checkBoth
Hours
Every 500 h
Date
Every 1 month
Due on
Whichever first
Time per job
2 h

Sample plant records from the Oxmaint portal's PM Schedules, captured 26 Nov 2026: 55 schedules, 10 of them meter based.

Wall planner calendar with coloured dots in a maintenance office

Compare the Rules on Real Schedules

Open sample PMs on dates, on hours and on both, and see when each comes due. Sign up to the micro app and look.

Which Rule for Which Machine

EWP annual inspectionA statutory check set by dateCalendar, 12 months
Dock leveler hydraulic and lip checkAgeing seals and hingesCalendar, 6 months
CNC ballscrew backlash checkYearly accuracy checkCalendar, 12 months
Grinder wheel guard checkWear with use, date as a back-stop500 h or 3 months
CNC way lube, spindle and coolantWear with use, date as a back-stop500 h or 1 month

Sample plant records from the Oxmaint portal's PM Schedules and PM Forecast, captured 26 Nov 2026.

How the Forecast Reads Hours

A date-based PM sits on its date. An hours-based PM is placed where the machine's own running rate says it will reach the interval.

Grinder wheel guard check, 500 h or 3 months
Hours left to the interval30 h
Running rate4.9 h a day

Sample plant records from the PM Forecast, captured 26 Nov 2026: the sample plant has 14 hours-led schedules in the forecast.

Technician reading the hour meter on an air compressor
Meter PMs need readings

An hours rule is only as good as the last reading. Log the hour meter at pre-start checks or with Log reading on the asset, and the forecast stays honest.

Expert Review
Reviewed by the Oxmaint AI maintenance team

Do not pick one rule for the whole plant. Put wear items on hours with a date back-stop, statutory and ageing checks on the calendar, and review a machine's schedule whenever its running pattern changes, such as a new shift or a line moving to a new product. Editorial guidance, not a quote from a named person.

Frequently Asked Questions

What is the difference between calendar and meter-based PM?
A calendar PM comes due on a date whether the machine ran or not. A meter-based PM comes due when the hour meter reaches an interval. Sign up to compare them.
Can one schedule use both?
Yes. A schedule on both rules is due on the hours or the date, whichever is reached first, and both roll on when the job is raised. Sign up to open one.
Which rule should I use?
It depends on how the part wears. Use hours for wear that follows use, dates for statutory or ageing checks, and both where a machine can sit idle. Sign up and review your schedules.
Where do the hour readings come from?
From readings logged on the asset, for example at a pre-start check or with Log reading on the asset page. The schedule reads the last reading the portal has. Sign up to log a reading.
How does the forecast place an hours-based PM?
From the machine's running rate: hours left to the interval divided by hours run per day gives the day it is expected to come due. Sign up to see the forecast.
Can I change a schedule's rule later?
Yes. Edit the schedule and change its interval or its rule when the machine's running pattern changes. Sign In to Access Micro App