A PM register answers one question: what is due now. A planner needs the next one: what lands over the coming weeks, and can the crew take it? Half of a plant's schedules may fall due on running hours, and no date on the record says when those hours will arrive. Oxmaint's PM Forecast projects each hour-based schedule from the machine's own hours a day, adds the calendar ones, and draws thirteen weeks of work against your crew's capacity. Sign up to try the micro app and open the forecast on a sample plant.
PM Forecast on Run Hours & Calendar
Ninety days of preventive work on hours and on the calendar, week by week, against what your crew can take. Sign up and open a sample forecast.
Thirteen Weeks on One Chart
This is the sample plant's forecast as it read on 26 November 2026: how many services fall in each week of the next ninety days. Click a week in the portal and the list below the chart shows exactly which jobs they are.
Sample plant records from the Oxmaint portal, captured 26 Nov 2026. Busiest week: 11 h of planned work against a crew capacity of 7 people x 40 h = 280 h a week. Your numbers will differ.
How an Hours-Based PM Gets a Date
A meter schedule has no due date of its own. Oxmaint works one out: the hours left until the service, divided by how many hours a day that machine actually runs. A schedule on both triggers lands on whichever gets there first, and the row says which.
A tow tractor that runs about 1,800 hours a year does roughly 5 hours a day. Its 250-hour service, with 175 hours left on the meter, lands about 35 days out, five weeks along the chart. Nothing on its record carries that date; the forecast works it out.
The Rows It Will Not Guess
If nobody knows how hard a machine runs, or its meter has never been read, the forecast cannot place the schedule honestly. Instead of inventing a date, it lists the schedule under Not placed with the reason: usage or reading missing. On the sample plant that list is empty, because every meter schedule has readings. Sign up and see how a missing reading is shown.
Fills gaps with an assumed date
Looks complete, hides uncertain rows
Surprises arrive when the hours do
Projects only from real usage and readings
Lists any row it cannot place, with the reason
Marks hours-led rows, so you can see machines working harder than planned
Open the Thirteen-Week Chart
Set your crew size and hours, click a busy week and see the jobs behind it. Sign up to the micro app and explore the sample forecast.
Capacity Is Your Two Numbers
The capacity line comes from two numbers you type: how many of the crew work planned jobs, and how many hours each a week. A week whose planned hours go over that line turns red. If the busiest week is far below it, the portal says so in plain words, as it does on the sample plant: 11 h at most against 280 h.
What the Ninety Days Are Made Of
Sample plant records, captured 26 Nov 2026.
Overdue Now, with a Raise Button
Above the weeks sits what is already late. Each row shows the service, the asset, how it falls due, hours left where it is on hours, the estimated time and who it is assigned to. You can raise one job or all of them.
| Service (sample plant) | Falls due on | Late by | Est. |
|---|---|---|---|
| Dock leveler hydraulic and lip check, every 6 months | Calendar | 9 days | 1 h |
| CNC ballscrew backlash and axis alignment, every 12 months | Calendar | 7 days | 6 h |
| EWP annual inspection, every 12 months | Calendar | 4 days | 3 h |
| Chiller and cooling tower water treatment, every 3 months | Calendar | 3 days | 3 h |
| Grinder wheel guard, spindle and way check, 500 h or 3 months | Calendar (30 h left at 4.9 h a day) | 2 days | 1 h |
Treat the forecast as a conversation with production, not a fixed plan. Look at the hours-led rows first: a machine reaching its service early is running harder than the schedule assumed, and that is worth knowing before it fails. Keep meter readings coming in, because an hours-based schedule is only as good as its last reading. Editorial guidance, not a quote from a named person.
Frequently Asked Questions
See the Next Thirteen Weeks Before They Arrive
Hours and calendar PMs on one chart, checked against your crew. Sign up and open the sample forecast.