How to Schedule a PM on Run Hours

By William Jerry on November 27, 2026

how-to-schedule-a-pm-on-run-hours-hero-compressed

A fixed calendar date is a poor guide for a machine that does not run the same hours every week. A press that stood idle for a fortnight does not need its 500-hour service yet, and a line that ran double shifts needs it early. Oxmaint AI lets you schedule preventive maintenance on running hours, on the calendar, or on whichever comes first, and its PM Forecast shows when the work will land. This guide walks through six steps. Sign up to try the micro app and follow along on a sample plant with 55 PM schedules.

PM Schedules · Run Hours · PM Forecast · Meter Readings

How to Schedule a PM on Run Hours

Create a PM schedule that comes due on running hours, on a calendar date, or on whichever is first, and see it on PM Forecast. Sign up and follow the steps on a sample plant with 55 PM schedules.

Six Steps From Hour Meter to Work Order

1
Check the machine has an hour reading

A run-hours schedule counts from the machine's hours today. Open the asset and use Log reading, or go to Meters & Utilisation. A machine that has never been read starts counting at its first reading.

Asset pageLog readingMeters & Utilisation
2
Create the schedule

Open PM Schedules and choose New Schedule. Name it, pick the asset and set Basis to Meter. Type the interval in Every, and the unit becomes Running hours. There is no Next due date to fill in, because the schedule falls due at its hours.

Schedule nameAssetBasis: MeterEvery: 500
3
Add the work

Enter the estimated hours, who it is assigned to and a task list. Parts can be listed too. Every work order the schedule raises carries the tasks and parts you set here.

Estimated hoursAssign toTask list
4
Add a calendar backstop if you want one

Open the schedule and change Basis to Both. Set the hours interval and the calendar interval, and the schedule falls due on whichever is reached first, such as every 500 hours or 1 month.

Basis: BothHours intervalCalendar date
5
Keep the hours current

Log a reading whenever someone reads the meter. Oxmaint refuses a reading lower than the last one, or one that implies more than 20 hours a day, and warns when the figure has not changed. Two readings give the machine a run rate.

Log readingRun rate
6
Read PM Forecast, then raise the job

PM Forecast places each schedule in one of the next thirteen weeks, and lists any it cannot place. When you are ready, use Raise job on the forecast, or Generate work order on the schedule.

Next 7 daysHours-ledNot placed

Try the Steps on a Sample Plant

Open PM Schedules, find a schedule set on running hours and see where it lands on PM Forecast. Sign up to the micro app and start with 55 sample schedules.

Hours or Calendar: Which Comes First?

With Basis set to Both, the two rules race. The job is raised by whichever side gets there first, and the forecast row says which one it was, so a planner can see a machine being worked harder than the plan assumed. Both examples below use the sample plant's schedule wording, every 500 hours or 1 month, whichever first. Sign up to set one up.

Busy machine
Illustrative example, not real data
Hours: 480 of 500
Calendar: 20 of 30 days
Hours come first
Quiet machine
Illustrative example, not real data
Hours: 210 of 500
Calendar: 30 of 30 days
Calendar comes first
Close-up of a technician writing down the hour meter reading on a CNC machine in daylight

How PM Forecast Places an Hours-Based PM

A date on the record cannot tell you when a machine will reach 500 hours, so Oxmaint projects it. It takes the hours remaining and divides them by the hours the machine runs each day. The example numbers are invented.

120 h
Hours remaining
÷
6 h
Hours a day
=
20 days
Until it falls due

Illustrative example, not real data.

The hours a day come from the machine's own typical usage if the plant knows it, or from the readings you have logged. With neither, the schedule is listed under Not placed instead of being given a guessed date, and it takes its place in the weeks as soon as a reading is logged. As readings come in, the projected dates move.

What Each Basis Asks You For

BasisYou enterNext due dateFalls due
TimeEvery number of weeks or monthsRequiredOn the date
MeterEvery number of running hoursNot usedWhen the machine has run the hours since its last service
BothAn hours interval and a calendar intervalCalendar dateOn whichever is reached first

The create form offers Time or Meter. Open the saved schedule to switch its Basis to Both.

Three Readings Oxmaint Checks

A run-hours PM is only as good as the readings behind it, so the portal tests each one before it is saved.

RefusedLower than the last reading. A meter does not run down; if it was replaced, record that instead.
RefusedMore than 20 hours a day since the last reading. This is usually a digit too many.
WarningSame as the last reading. It is saved, but the machine will look unused since then.

Where It Lands: The Sample Plant's Forecast

The sample plant has 55 PM schedules: 51 active, 6 overdue, 10 due this week and 10 meter based. Its PM Forecast turns them into a thirteen-week picture. Sign up to open the forecast.

portal.oxmaint.ai · PM Forecast
6
Overdue now
10
Next 7 days
24
Next 30 days (42 h of work)
14
Hours-led
0
Not placed
Next 90 days, services by type
CNC way lube, spindle and coolant check6
Conveyor chain, belt and drive inspection5
Forklift 250 h service4
Hydraulic oil, filter and light curtain check3
Press clutch, brake and stopping-time test2
Robot cell: torch, liner, cables and safety fence2
One schedule, two triggers
Grinder wheel guard, spindle and way check
Every 500 hours or 3 months, whichever first
30 h left, running 4.9 h a day
The hours side would be due in about six days.
Due now, 2 days late, on the calendar
The date side got there first, so that is the trigger shown.

Sample plant records from the Oxmaint portal, captured 26 Nov 2026. Hours-led means the schedule reaches its hours before its date. Your numbers will differ.

Maintenance planner at a desk comparing a printed thirteen-week planning chart with a laptop in daylight
Expert Review
Reviewed by the Oxmaint AI maintenance team

Run-hours PMs repay the effort on machines whose use swings, such as presses, CNC cells and forklifts. Pick a regular day for reading meters and give one person the job, and add a calendar backstop on anything where a date still matters. Check the Not placed list each week, because every row on it needs a reading or a usage figure. Editorial guidance, not a quote from a named person.

Frequently Asked Questions

What is the difference between a run-hours PM and a calendar PM?
A calendar PM comes due on a date, whether or not the machine ran. A run-hours PM comes due when the hour meter has advanced by the interval, which suits machines that do not run the same hours each week. Sign up to set up both kinds.
Can one schedule use both hours and the calendar?
Yes. Open the schedule and change Basis to Both. It then falls due on whichever is reached first, for example every 500 hours or 1 month, and PM Forecast shows which side brought it forward. Sign up to try a dual-trigger schedule.
What if the machine has never had a meter reading?
The schedule waits for its first reading, which becomes the starting figure. Until then PM Forecast lists it under Not placed rather than guessing a date. Log a reading on the asset page or on Meters & Utilisation. Sign up to log your first reading.
How does PM Forecast know when an hours-based PM will fall due?
It divides the hours remaining by the hours a day the machine runs, taken from its usual usage or from the readings you logged, and places the service in one of the next thirteen weeks. It moves as new readings arrive. Sign up to open the forecast.
Does the work order raise itself?
You raise it. Use Generate work order on the schedule, Raise job on PM Forecast, or Raise jobs for due PMs on the PM Schedules page for everything already due. The job carries the schedule's tasks and parts. Sign up and raise your first job.
Can I try this without setting anything up?
Yes. The portal starts with a ready-made plant, so you can look at the records straight away. When you are ready, add your own machines under Assets, or send your asset list, parts and stock, PM schedules and work order history (an export from your current CMMS or a spreadsheet is enough) and they are loaded in place of the starting records. Sign In to Access Micro App

Schedule Maintenance on the Hours a Machine Really Runs

Run-hours PMs, calendar PMs and a thirteen-week forecast in one portal. Sign up, explore the sample plant, and add your own meters when you are ready.


Share This Story, Choose Your Platform!