New Equipment Commissioning Checklist (Installation, FAT, SAT & Acceptance Testing Guide)

By Johnson on March 26, 2026

equipment-commissioning-checklist-installation-fat-sat-acceptance

Every new piece of industrial equipment that enters service without a structured commissioning process is a liability from day one — not an asset. Studies consistently show that fixing a defect identified during a Factory Acceptance Test costs ten times less than fixing the same defect after site installation, and ten times less again than discovering it during production. The commissioning process — from FAT at the manufacturer's facility through SAT at your site, mechanical installation verification, performance baseline, and preventive maintenance setup — is the single most important phase in an asset's entire lifecycle. Miss a step here and you inherit problems that compound for the next ten years. This checklist covers all five commissioning phases in sequence, structured so that maintenance engineers, reliability teams, and project managers can use it as a live digital record in Oxmaint — linked to the asset from its first day in your facility.

Asset Lifecycle Management

New Equipment Commissioning Checklist

Installation · FAT · SAT · Performance Validation · PM Setup

01
FAT Factory Acceptance Test
02
INS Mechanical Installation
03
SAT Site Acceptance Test
04
PER Performance Validation
05
OEE OEE Baseline & PM Setup
Cost of Defect Detection — Why Commissioning Phase Matters

At FAT

Post-Install SAT 10×

After Commissioning 50×

During Production 100×

Relative cost of identifying and correcting the same equipment defect at each stage of the commissioning lifecycle. Source: industry commissioning best practice references.

Phase 01 — FAT

Factory Acceptance Test — Vendor Site Verification Before Shipment

The FAT is your last cost-effective opportunity to reject or remediate equipment before it ships. Once an asset leaves the manufacturer's facility, every defect you find becomes your logistical and financial problem. The FAT is governed by IEC 62381:2024 for automation systems and mirrors the ISPE Baseline commissioning and qualification framework in regulated industries. Sign up for Oxmaint to run the FAT checklist as a digital form linked to the new asset record from the moment of PO issuance.

FAT Factory Acceptance Test — Vendor Facility Before equipment dispatch
Documentation review — drawings, data sheets, certifications
Verify the complete documentation package against the Purchase Order and User Requirements Specification (URS): P&ID drawings, electrical schematics, mechanical drawings, data sheets for all major components, material certificates, weld inspection records, pressure test certificates, and CE/UL compliance documentation. Any missing document is a hold point — do not sign off FAT completion until the full documentation package is confirmed and handed over. Log the documentation checklist outcome in Oxmaint against the asset record.
All PO-specified documents: received and verified. Missing certificates: hold point — do not release for shipment.
Physical and dimensional inspection — as-built vs. drawing
Inspect the equipment physically against the approved fabrication drawings. Check overall dimensions, connection point locations (utility inlets, electrical terminations, instrument tapping points), access door clearances, lifting lug positions, and nameplate data. Dimensional errors in connection point locations are among the most expensive post-installation discoveries — a utility connection that does not align with the site layout requires field modification under time pressure during installation.
All critical dimensions: within drawing tolerance. Connection locations: match site layout drawing. Nameplate: matches spec.
Functional testing — all control modes, interlocks and safety functions
Witness functional testing of all operational modes (manual, automatic, emergency stop), all safety interlocks, and all alarm setpoints. Each interlock should be tested by inducing the fault condition and verifying the correct protective response — not just by bypassing the sensor and confirming the PLC logic output. Document each interlock test result with the test condition, expected response, and actual response in the FAT test record in Oxmaint.
All interlocks: tested by fault induction, not bypass. All alarms: confirmed at correct setpoints. E-stop: verified on all axes.
Punch list management — open items before shipment release
Categorise all non-conformances identified during FAT into Category A (shipment hold — must be resolved before equipment leaves the factory), Category B (must be resolved before SAT sign-off), and Category C (minor items to be resolved within agreed post-commissioning timeframe). The shipment release should only be authorised when all Category A punch list items are closed and verified. Log the punch list in Oxmaint as corrective work orders against the asset, with owner and target date assigned.
Category A items: zero at shipment release. Category B: agreed resolution plan. Category C: documented with agreed dates.
Prevents
Dimensional incompatibility discovered during on-site installation at 10× the correction cost
Missing documentation that blocks regulatory qualification or insurance acceptance
Interlock failures discovered during production at risk to personnel and product
Phase 02 — INS

Mechanical Installation — Site Preparation, Alignment & Utilities

Installation quality determines how the equipment performs for the next decade. A machine that is installed 0.3mm out of level, with a coupling misaligned by 0.1mm, or anchored with insufficient torque on the baseplate will generate vibration that destroys bearings on a schedule that looks like random failure — until a precision maintenance audit traces every bearing replacement back to the original installation error. Book a demo to see how Oxmaint captures installation measurement records against the asset for lifetime trend analysis.

INS-A Civil & Mechanical Before equipment energisation
Foundation and anchor bolt verification
Confirm foundation dimensions against equipment drawing, verify anchor bolt positions and projection, check concrete cure certification (minimum 28-day cure for dynamic equipment foundations), and confirm bolt torque to specification using a calibrated torque wrench. Log torque values per bolt in Oxmaint installation record.
Bolt torque: per spec ±5%. Concrete: 28-day cure minimum. Foundation: within 1mm of drawing layout.
Levelling and alignment — machine baseplate
Measure baseplate level across all levelling pad positions using a precision spirit level or laser level. Record readings in both X and Y axes at each pad. Adjust levelling pads to bring the baseplate within the equipment OEM tolerance — typically 0.1mm/m for precision machinery. Document all final readings before grouting.
Level: within 0.1mm/m for rotating machinery. 0.2mm/m for general purpose. Log all readings before grouting.
Shaft and coupling alignment — laser alignment results
Perform laser shaft alignment after final grouting and utility connection, with the machine at operating temperature where thermal growth is a factor. Record parallel and angular misalignment values for both vertical and horizontal planes. Compare against OEM tolerance — most coupled rotating equipment requires alignment within 0.05mm parallel and 0.05mm/m angular. Log the alignment report to Oxmaint as a baseline for future predictive maintenance comparison.
Parallel: <0.05mm. Angular: <0.05mm/m. Re-check after first 500 hours of operation.
INS-B Utilities & Electrical Before first power-on
Electrical supply — voltage, phase sequence and earth continuity
Before connecting equipment power, verify supply voltage at the isolator is within equipment tolerance (typically ±10% of rated voltage), confirm phase sequence matches equipment rotation requirements, verify earth continuity from the equipment chassis to the main earth bar, and confirm cable sizing meets the equipment rated current with correct overload protection. Document supply voltage, phase rotation, and earth resistance in Oxmaint.
Voltage: rated ±10%. Phase sequence: confirmed before motor connection. Earth resistance: <1 ohm.
Utility connections — air, water, gas, steam — pressure and flow
Verify each utility connection is made to the correct port (cross-connection errors are a common cause of equipment damage at first start), confirm supply pressure at the equipment inlet is within the rated range, and pressure-test all connections before energising. For cooling water systems, flush the supply line before connecting to the equipment heat exchanger to prevent debris ingress.
All utilities: connected to correct ports, confirmed by drawing. Supply pressure: within rated range. No leaks at hydraulic test.
Instrument calibration — all installed sensors and transmitters
Verify calibration certificates for all instrumentation installed on the equipment — pressure transmitters, temperature sensors, flow meters, level switches, and position sensors. Calibration should be traceable to a national standard and completed within 12 months. Any sensor installed without a calibration certificate is a data quality risk that will invalidate performance testing during SAT.
All instruments: calibration certificate within 12 months, traceable to national standard. Uncalibrated: replace before SAT.
Every installation measurement. Every alignment reading. Every punch list item. Oxmaint links every commissioning record to the asset from day one — giving you a complete history from first bolt to first breakdown, if one ever comes.
Phase 03 — SAT

Site Acceptance Test — Integration, Environment & Operational Readiness

The SAT validates what the FAT could not — how the equipment performs in its actual operating environment, integrated with your plant systems, utilities, and control architecture. Transport, installation, and environmental differences between the factory and site regularly surface issues that passed FAT without triggering any defect. The SAT is your final gate before production handover. Sign up for Oxmaint to run SAT as a parallel digital workflow to the FAT record, with deviation tracking linked to the same asset.

SAT Site Acceptance Test — Customer Site After installation, before production handover
FAT Scope
Vendor facility, controlled environment
Design spec compliance
Component-level functional test
Simulated load conditions
Shipment release decision
vs
SAT Scope
Customer site, real environment
Integration & interface compliance
System-level functional test
Actual production load conditions
Production handover decision
Transport damage inspection — pre-energisation visual check
Before any electrical connections are made, inspect the equipment for transport damage: cracked instrument glasses, damaged cable trays, bent pneumatic tubing, loose terminal connections, and any evidence of impact damage to the structure or control cabinet. Document and photograph all findings in Oxmaint. Any structural damage or confirmed instrument impact should trigger a Category A hold — the FAT testing that validated the instrument readings is now invalid if the instrument was subject to impact.
No structural damage, no cracked instruments, no loose terminals. Any impact evidence: photograph and raise hold before energising.
Control system integration — DCS/SCADA/PLC interface verification
Verify communication between the equipment control system and the site DCS, SCADA, or MES layer — signal mapping, tag naming conventions, alarm priority levels, and data historian integration. Test each hardwired interlock between the equipment and site safety systems (e.g., fire and gas system, area ESD) by inducing the signal at the site system and confirming the correct response at the equipment. A common SAT failure mode is alarm setpoints that were correctly configured in factory but were overwritten during integration testing.
All signals: mapped and verified at DCS/SCADA. All site interlocks: tested by signal induction. Alarm setpoints: confirmed post-integration.
Operational run test — continuous operation under production conditions
Operate the equipment continuously at production load for the SAT run period (typically 72–168 hours depending on equipment complexity and industry requirements). Monitor all key parameters — temperature, pressure, vibration, current draw, cycle time — against the FAT baseline. Any parameter that trends outside the FAT baseline range during the SAT run represents a site-environment effect that must be investigated before handover. Log all SAT run data in Oxmaint as the asset's performance baseline.
Run period: minimum 72 hours continuous at production load. All parameters: within FAT baseline ±10%. Any deviation: investigate before handover.
Operator training confirmation — sign-off before handover
Confirm that all operators who will run the equipment have completed the OEM-specified training and that training records are documented. A machine handed over to untrained operators will generate failures that look like equipment defects but are actually operating errors — invalidating the warranty and generating unnecessary maintenance calls. Record training completion in Oxmaint against each operator's profile linked to the equipment asset.
All shift operators: OEM training completed and documented. Maintenance technicians: trained on first-line maintenance procedures.
Validates
Equipment integration with site control systems before production handover
Transport damage impact on instrument calibration and structural integrity
Continuous operational stability under real production load conditions
Phase 04 — PER

Performance Validation — Capacity, Quality Output & Efficiency Confirmation

Performance validation answers the question the business actually cares about: does this equipment produce the output at the quality and rate specified in the purchase contract? The SAT confirms the equipment operates — the performance validation confirms it operates at specification. These are different tests with different acceptance criteria. Book a demo to see how Oxmaint records performance validation results against the asset and flags deviations from contractual specifications.

PER Performance Validation — Post-SAT, Pre-Warranty Period First 30 days of production operation
Rated Throughput
Measure actual throughput over a minimum 5-shift production run and compare against the contractual rated capacity. Throughput below 95% of rated at full load conditions is a contractual non-conformance that must be raised with the vendor before the warranty period starts.
Target: ≥95% of rated capacity at full load
Product Quality Output
Measure first-pass quality rate (products meeting specification without rework) over the validation period. Document quality failures by defect type — systematic defects traceable to equipment setup indicate a commissioning error, not a production process issue.
Target: first-pass quality rate per contractual spec
Energy Consumption
Record energy consumption per unit of output and compare against the OEM rated specific energy figure. Consumption more than 10% above rated indicates either an installation issue (alignment, friction) or a process parameter deviation. Log kWh per production unit to Oxmaint as the energy efficiency baseline.
Energy per unit: within 10% of OEM rated specific energy
Cycle Time Verification
Measure actual cycle time against the design cycle time across all production modes. Cycle time variation greater than 5% from design indicates either a mechanical speed restriction, a control parameter error, or a process input quality issue that needs to be distinguished from an equipment deficiency.
Cycle time: within ±5% of design across all modes
Confirms
Contractual capacity commitments before warranty period commences
Energy efficiency baseline for ongoing sustainability tracking in Oxmaint
Systematic quality defects attributable to equipment vs. process before handover acceptance
Phase 05 — OEE & PM

OEE Baseline & Preventive Maintenance Setup — Asset Lifecycle Foundation

The commissioning phase ends when the OEE baseline is set and the preventive maintenance programme is active in your CMMS. An asset that completes SAT and performance validation but enters production without a PM schedule and OEE measurement framework will degrade on an unmanaged trajectory. The first 90 days of production operation establish the baseline that every future reliability discussion will reference. Sign up for Oxmaint to configure OEE tracking and PM work orders in the same platform where your commissioning records live.

OEE OEE Baseline & PM Configuration — Asset Handover At production handover — before first production shift
OEE = Availability × Performance × Quality
Availability Planned production time minus unplanned downtime, divided by planned production time. Target baseline: ≥90% for new equipment in first 90 days.
Performance Actual throughput versus ideal throughput at rated speed. Target baseline: ≥95% for equipment completing successful performance validation.
Quality Good units produced versus total units started. Target baseline: ≥98% for equipment with confirmed first-pass quality rate at performance validation.
Asset record creation — full bill of materials in Oxmaint
Create the complete asset record in Oxmaint at commissioning handover: asset name, tag number, location, manufacturer, model, serial number, installation date, warranty expiry, and full bill of critical spare parts. Attach the FAT report, SAT report, installation measurement records, alignment report, and performance validation data to the asset record. This is the asset's permanent digital file — everything linked to one record, accessible from day one.
Complete asset record: all data fields populated, all commissioning documents attached before production start.
Preventive maintenance plan — OEM schedule loaded into Oxmaint
Load the OEM-specified preventive maintenance schedule into Oxmaint as recurring work orders at commissioning handover — not after the first breakdown. The PM schedule should be structured by operating hours and calendar intervals as specified in the OEM maintenance manual, with each task linked to the required spare parts, tools, and estimated labour time. Starting the PM clock from the installation date means the first scheduled maintenance event will trigger at the correct interval.
All OEM PM tasks: loaded in Oxmaint before first production shift. PM clock: started from installation date.
Critical spare parts — initial stock confirmed against OEM recommendation
Verify that the initial stock of critical spare parts recommended by the OEM (typically bearings, seals, filters, belts, and control system modules with long lead times) is available in stores before the equipment enters production. A new equipment breakdown requiring a six-week lead-time bearing in the first month of operation is entirely avoidable — and represents a commissioning failure, not a maintenance failure.
All OEM-recommended critical spares: confirmed in stores or on order. Lead-time items: order placed at commissioning.
Vibration and condition monitoring baseline — first measurement at commissioning
Take vibration baseline measurements on all rotating elements (motor bearings, gearbox, pump) during the SAT run period, while the equipment is in good known condition. These baseline readings — logged in Oxmaint against the asset — are the reference against which all future condition monitoring readings will be compared. A bearing failure identified as a 2× increase from baseline is a meaningful finding. Without a baseline, every future reading is absolute rather than relative and far less actionable.
Baseline vibration: measured at all bearing locations during SAT run. Logged in Oxmaint before production handover.
Establishes
OEE measurement framework before the first production shift creates the baseline
PM schedule active from day one — not after the first breakdown reveals the gap
Condition monitoring baseline that makes future predictive maintenance meaningful
Field Outcome

What Structured Commissioning Changes — A Documented Case

"

We commissioned a high-speed packaging line using the Oxmaint five-phase checklist. During FAT, we identified three Category A punch list items — two interlock configuration errors and a dimensional mismatch on the air supply manifold position that would have required a field modification. Both were resolved at the vendor's facility. During SAT, we found a control integration issue with our site DCS that the vendor's factory environment could not have replicated. The SAT run data — 96 hours continuous — became the OEE baseline we use today, 18 months later. We started PM work orders on the day of handover. In the first year, we ran 97.2% availability against a target of 90%. The commissioning record in Oxmaint has been referenced four times — once for a warranty claim, twice for maintenance troubleshooting, once for an insurance audit. Every time, the data was there.

— Reliability Engineer, Food & Beverage Manufacturing, UK, 2025
FAQ

Equipment Commissioning — Common Questions

What is the difference between FAT, SAT, and commissioning?

FAT (Factory Acceptance Test) is performed at the manufacturer's facility before shipment to verify the equipment meets design specifications in a controlled environment. SAT (Site Acceptance Test) is performed at the customer's site after installation to verify integration with site systems and performance under real operating conditions. Commissioning is the broader process of activating and optimising the equipment for production — FAT and SAT are the validation gates within that process. Sign up for Oxmaint to manage all three phases from a single asset record with linked documentation and punch list tracking.

How long should the SAT run period be before accepting the equipment?

Industry standard guidance from ISPE and IEC 62381:2024 recommends a minimum 72-hour continuous run at production load conditions for standard industrial equipment. For complex or regulated environments (pharmaceutical, food grade, pressure systems), the SAT run is typically 168 hours (one week) without unplanned interruption. Any unplanned stop during the SAT run resets the clock — the run period must be completed continuously to confirm operational stability. Book a demo to see how Oxmaint structures the SAT run period logging with timestamped start, stop, and deviation records.

When should the OEE baseline be established — during commissioning or after a run-in period?

The OEE baseline should be established during the SAT run period, not after an arbitrary run-in interval. The SAT run, conducted at production load with all systems operational, represents the best available baseline for a newly commissioned asset. Waiting for a "run-in period" typically means the first 30–90 days of production data are never formalised as a baseline — and the team loses the reference point that distinguishes early-life degradation from commissioning defects. Oxmaint captures OEE data from the first production shift and compares it against the SAT run baseline automatically.

Can this checklist be used for equipment upgrades and retrofits, not just new equipment?

Yes — for major upgrades and retrofits, the FAT phase applies to any vendor-supplied components or sub-systems, the INS phase covers the installation of the upgrade, the SAT phase validates integration with the existing plant systems (which is often more complex than for new equipment because legacy interfaces must be maintained), and the performance validation and OEE phases rebaseline the upgraded asset's performance. Book a demo to configure a retrofit-specific commissioning template in Oxmaint that links the new commissioning record to the existing asset history.

How does Oxmaint link the commissioning record to ongoing maintenance management?

Every commissioning record in Oxmaint — FAT report, SAT run data, alignment readings, vibration baseline, performance validation results — is attached to the asset record and accessible from the same interface used for daily work orders, PM scheduling, and condition monitoring. When a maintenance technician raises a work order for a bearing failure 18 months after commissioning, the original alignment report and vibration baseline are one click away — making root cause analysis faster and more accurate. Sign up for Oxmaint to experience the full asset lifecycle record from first bolt to final decommission.

Five Phases. One Asset Record. Zero Paper Trails.

Start Commissioning the Right Way — From Day One

Every phase of this checklist exists because a maintenance problem — a bearing failure, a warranty dispute, an unexplained quality defect — has been traced back to a commissioning step that was skipped, undocumented, or lost in a paper folder. Oxmaint gives every commissioning check a timestamp, a photo record, an asset link, and an escalation path — so the documentation that protects your investment is always there when you need it.


Share This Story, Choose Your Platform!